Precision HDPE spooling future-proofs iron ore mine

Precision HDPE spooling future-proofs iron ore mine

Precision HDPE spooling future-proofs iron ore mine

In 2022, Advanced Piping Systems supplied HDPE spooling and pipe for an A$100 million water management upgrade project. The project was at an iron ore mine in the Pilbara region of Western Australia. 

The project aimed to increase the mine’s reverse osmosis (RO) plant capacity from 10 to 40 mega litres. This was achieved in partnership with a leading national industrial services provider and a top national water and waste treatment company. Future-proofing its operations for the next 20 years.

As part of upgrading the RO plant, we first delivered precision poly pipe spooling and then supplied the interconnecting HDPE piping to link the new RO plant to the mining infrastructure.

Our Business Development Manager (SA/NT), Paul Narancic, shares how the team successfully delivered the project despite many challenges. 

Rising to the challenge

We split the project into two stages. The first stage, completed in 2018, involved treating brackish water. While the second stage, completed last year, saw the plant increase its capacity.

Paul explained that washing ore from the mine is essential to remove chloride-based salts and requires a huge amount of water.

“Stage 1 involved constructing a 10 megalitre plant to treat the ‘brackish’ water, which is salty, but not as salty as seawater. 

“As the mine ages, the feed of water into the system becomes saltier. So, in Stage 2, a much larger RO plant was built to increase the mine’s water processing capacity from 10 to 40 mega litres.

“This increase ensured a plentiful supply of clean water for processing over the life of the mine.”

Advanced Piping Systems secured this job because of our fabrication capability, adaptable team, and dedicated workforce. Our digital QA systems and network of global suppliers also played a crucial role.

“There was a complexity to the project, which required our experience and an in-depth knowledge of HDPE systems,” Paul said.

“When our competition said ‘no’, we said ‘yes’…we made a commitment to deliver — and we did exactly that.”

Delivering on our word

According to Paul, the project presented many challenges. This included exceedingly tight timelines, maintaining spool accuracy from isometric drawings, temperature deflection, and distance to the site. 

“These spools required far greater accuracy than the Australian Standards suggest, so there was a big challenge using isometric drawings to supply accurate piping to a project 3,300 kilometres away,” he said. 

“The plant spools were fabricated with high accuracy because they were required to be installed in a purpose-built modular framework. 

“To take into account temperature deflection, we suggested additional breakpoints to allow for greater adjustment on site. 

“We also added “green” pipe to the spools for the interconnecting section, so they could be cut and adjusted on site to suit changes from the original iso drawing.”  

Advanced Piping Systems put on double labour shifts, weekend work, and a constant stream of trucks moving through the yard to meet the tight deadlines for the interconnecting section. There was also extra staff to assist our designated full-time project management resources and ensure the project’s success.

The Advanced Piping team conducted weekly video updates to overcome the distance to the site. We also flew to Perth for face-to-face project updates during the fabrication process. Additionally, We developed an online spool tracker, allowing us to track each spool through the production process with an ETA.

All in all, the team delivered more than 1,500 spools and supplied pipe ranging from 900mm to 1200mm, along with 7,500 fittings. They spent over 5,000 hours working on the project. Everyone involved put in a huge effort!

For reliable HDPE fabricator and supplier, Contact our knowledgeable customer service team today.

Related Articles

Bespoke reverse osmosis system provides clean drinking water in the Philippines

Water contamination is a common and widespread health risk throughout South-East Asia. To purify drinking water in many countries across this region, a process called …

Beyond pipes – your mining questions answered

Mine projects are inherently unique, each presenting a set of challenges and specifications that require customised solutions. However, it’s often surprising how many questions that …

How to reduce a flange size while maintaining a consistent pipeline ID

Maxi Stub flanges

Maxi stub flanges — comprising a hybrid stub flange and backing ring — are a quick and effective solution to reduce a flange size whilst …